Keene awarded $1 million downtown revitalization grant; sidewalks and park infrastructure slated, skate park ineligible
Summary
Keene staff said the city is expected to receive a $1 million downtown revitalization grant (with a $50,000 match). Sidewalks, park lighting and food-truck electrical infrastructure are planned; staff said the grant cannot fund the skate park because environmental/site studies were required.
Get email alerts on the Downtown Revitalization topic
No spam. Unsubscribe anytime.
Keene’s EDC Type B board heard on Wednesday that the city is slated to receive a $1 million downtown revitalization grant with a $50,000 local match. City Manager Mera told the board the grant's timeline and project requirements prevented the city from using the funds for the planned skate park.
"I wasn't able to use that money towards a skate park," Mera said, explaining that the skate-park site would have required soil samples and environmental studies the grant timeline did not allow.
Staff said the grant will instead fund sidewalks connecting the gym to the park, pedestal lighting for the walking path, and new infrastructure to support events — including dedicated electrical outlets for food trucks and booth vendors. The packet map (page 5) shows conceptual placement; engineers are updating detailed plans.
Mera said the grant administrators suggested additional items staff could add if money remains, such as a larger pavilion and repaving the park parking lot. An earlier estimate for curb and sidewalk work tied to a proposed road was about $219,000; a prior quote to extend sidewalks from the gym to the park was roughly $350,000 before engineers revised scope to trim retaining-wall costs.
Board members pressed staff on where the revitalization district would extend. Mera said the district had to be drawn to keep roughly 80% commercial property within the boundary to meet grant eligibility, which is why the map narrows around university-owned parcels.
The board also discussed a potential pedestrian crossing funded by TxDOT; Mera said the city is coordinating with TxDOT and that the agency would likely be the funder for a crossing across S. O Betsy.
Mera emphasized that the grant money is intended to improve quality-of-life projects in public spaces: "a lot of this money is going to go into what I would consider be board-quality-of-life type things for the city," she said. Staff will return with detailed engineering costs and a finalized map in a future packet.