Board approves $1.02 million amendment for sludge drying and construction management

Waukesha Board of Public Works · April 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved amendment No. 3 with Strand Associates for construction management on the biogas purification and sludge drying project, adding $1,020,600 for on‑site engineering and construction administration focused on sludge drying and major electrical upgrades.

The Waukesha Board of Public Works on April 17 approved contract amendment No. 3 with Strand Associates, adding $1,020,600 for construction management services tied to the biogas purification and sludge drying facilities enhancements project.

Public Works staff said the amendment covers additional engineer and construction-management hours needed on site while equipment — including sludge dryers, generators and electrical upgrades — are installed. Staff also reiterated that the biogas reuse portion had previously been removed from the project because selling recovered gas back to We Energies proved not economically feasible; the amendment therefore focuses on sludge drying and associated electrical work.

"This is the charge for this change order is $1,020,600," the Public Works staff member said, and noted the construction-administration budget and overall project remain favorably positioned relative to the total budget to date. Committee members asked about future uses of space freed by new equipment; staff said reuse and storage options are being considered.

The amendment was approved by Board vote; staff will continue construction oversight as the project moves into the next phase.