Broken Bow approves $65,357 change order to extend Eagle Crest storm pipe

City of Broken Bow City Council · July 9, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order 1 for the Eagle Crest Subdivision totaling $65,357 to extend storm piping 350 feet (75 ft of 24-inch pipe and 275 ft of 18-inch pipe), fill the ditch, add inlets and extend across Hillcrest Drive to facilitate future storm sewer connections.

The Broken Bow City Council on July 9, 2024, approved Change Order 1 for the Eagle Crest Subdivision project in the amount of $65,357. The motion, made by Councilmember Russ Smith and seconded by Councilmember Paul Holland, passed with aye votes from Smith, Wassom and Holland; Councilmember Chris Myers abstained.

Ryan Kavan of JEO explained that the change order covers an extension of storm sewer pipe by 350 feet beyond the originally proposed terminus at Linden Drive. The work includes 75 feet of 24-inch pipe and 275 feet of 18-inch pipe, backfilling an existing ditch with pipe and soil, installation of inlets, and extending the line across Hillcrest Drive. The additional piping will allow the city to connect to the line in the future if it decides to install a storm sewer along Hillcrest Drive.

Council members asked procedural questions; no amendments to the dollar amount were proposed during the meeting. Councilmember Myers recorded an abstention on the roll-call vote.