Engineer reports on 2026 road program, sidewalk bidding and Mill Street demolition
Summary
The borough engineer told council that 2026 road program documents are complete, Springfield Road sidewalk contract documents are on PennBid with a June 25 bid opening, demolition at 32 Mill Street has begun and is expected to finish within four weeks, and Madison Avenue stormwater plans require a minor change because of a sewer lateral conflict.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
At the meeting the borough engineer provided progress updates on several public-works projects.
The engineer said documents for the 2026 road program have been completed and forwarded for review, and that demolition at 32 Mill Street has begun with most of the structure down and an estimated completion timeline of about four weeks. He reported a minor revision is needed for Madison Avenue stormwater work because of a conflict with a sewer lateral, and that Springfield Road sidewalk contract documents are now on PennBid with a bid opening set for June 25.
Councilors asked whether the sidewalk work or alternates would affect the liquid-fuel timeline tied to county aid; the engineer said sidewalk work should not impact the road program timing and noted projects must be completed and MS-999 forms submitted and approved by the end of October to avoid risking county aid.