Town awards Meadow Hill I&I mitigation contracts to Whispering Pine and Insituform

Town Board of the Town of Newburgh · October 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Town of Newburgh approved an amendment for post-bid engineering services (costs capped unless further action) and awarded two Meadow Hill I&I mitigation construction contracts: Whispering Pine Development for general construction ($1,616,625) and Insituform Technologies for trenchless work (base $959,000).

Representative Patrick J. Hines, speaking for the town engineer, asked the board to approve Amendment No. 1 to the MHE Engineering contract to perform post-bid construction services for the Meadow Hill I&I mitigation project; the amendment authorizes post-bid hourly services with a proviso that costs will not exceed $275,000 without additional board action.

The board then considered bids and awarded Meadow Hill I&I Mitigation Contract 1-GC (general construction) to Whispering Pine Development on a base bid of $1,616,625.00 after the town received four bids. For Contract 2-GC (trenchless construction), the board awarded to Insituform Technologies, LLC with a base amount of $959,000.00 (the minutes also list an alternate price of $1,666,850.00). Motions to approve the amendment and to award both contracts passed unanimously.

Why it matters: the Meadow Hill I&I project addresses infiltration and inflow issues in the Meadow Hill subdivision and is funded through the town’s sewer capital accounts; awarding contracts moves the project from procurement into construction planning. Hines noted that post-bid engineering services would proceed on an hourly basis and that the town must authorize any expenditures beyond the $275,000 threshold.

What’s next: the engineering firm and awarded contractors will coordinate for post-bid services and construction scheduling; the town flagged that costs above the stated threshold require additional board approval.