Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Parks And Recreation topic

No spam. Unsubscribe anytime.

Lyons council approves $104,253 Pay App and authorizes $85,709 CDBG drawdown for park project; change order tabled

City of Lyons Mayor and Council · June 8, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Nelson Construction Pay App #5 for $104,253.33 for the Lyons Park Improvement Project and authorized CDBG Drawdown #14 for $85,709.16 to cover the payment, engineering and admin fees; a $8,538.75 change order from Nelson Construction was tabled because materials breakdown was not provided.

The Lyons City Council on June 8 approved Payment Application #5 for the Lyons Park Improvement Project and authorized the corresponding CDBG drawdown to cover construction, engineer and administrative fees.

Councilmember Jay Maddox moved to approve Pay Application #5 from Nelson Construction in the amount of $104,253.33; Councilmember Tyler Vacha seconded the motion, which passed on a 3–0 roll call (Councilmember Kyle Phillips absent). At the same time, councilors authorized Drawdown #14 of CDBG grant 23PWF003 for $85,709.16 to cover Pay App #5, JEO engineer fees and NENEDD administrative and construction fees. The minutes record a required local match of $21,130.42 to be transferred from General MM and that a line-of-credit request will equal Drawdown #14.

Separately, Nelson Construction was not present to discuss Change Order #1 (for $8,538.75 covering one-hour fire-rated walls and ceiling in the pavilion mechanical room). Because the contractor had not provided a materials breakdown, the council voted to table the change order (motion by Vacha, seconded by Maddox; carried 3–0).

The minutes do not include further detail on the construction schedule or the engineer’s invoice breakdown; Nelson Construction’s absence and the missing materials breakdown were cited as the reason for tabling the change order.