Broken Bow council approves sewer change orders, votes to notify county to renegotiate communications agreement
Summary
Council approved two change orders on the Highway 2 sanitary sewer project — moving completion to March 1, 2025, and adding concrete protection for $9,280 — and unanimously authorized a one-year notice to Custer County to renegotiate the Custer County Communications Center interlocal agreement.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
The Broken Bow City Council on March 3 approved two change orders on the Highway 2 Sanitary Sewer Extension project and authorized the City Administrator to send one-year notice to Custer County to terminate the current interlocal agreement for the Custer County Communications Center, a procedural step to begin renegotiation.
Change Order #1: The council approved a revision moving the project’s substantial completion date from Dec. 1, 2024, to March 1, 2025. The motion passed with two ayes and one abstention (Joe Wamsley).
Change Order #2: The council approved adding an 8-inch by 8-foot concrete section with rebar spaced at 24 inches on center to protect the sewer main for approximately 80 linear feet at a cost of $9,280.00. The vote was recorded with two ayes and one abstention (Wamsley).
Resolution 2025-01: The council approved a resolution directing the City Administrator to send notice to Custer County that the City desires to terminate the existing interlocal cooperative agreement for the Custer County Communications Center; Mayor Rod Sonnichsen said the one-year notice is required to reopen negotiations. That resolution passed unanimously (ayes: Smith, Wamsley, Holland).
JEO Consulting Group Inc. is the consulting/contracting firm referenced in the change orders; the meeting record does not include the full change-order documents or a revised contract amount beyond the $9,280 line item for Change Order #2. Councilmembers did not elaborate further on schedule mitigation or penalty provisions in the public minutes.