Council authorizes design contract for Clear Creek Water Reclamation Plant; $45.5M design phase for $455M project

Denton City Council · June 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved a professional services contract (not to exceed $45,528,839) for design and construction‑phase services for the Clear Creek Water Reclamation Plant, a 10 million‑gallon‑per‑day advanced treatment facility; staff said construction is estimated at about $455 million and the TCEQ discharge permit was approved in 2025.

The Denton City Council authorized the city manager to execute a professional services agreement for design and construction support of a new Clear Creek Water Reclamation Plant. Kyle Pedego, planning and engineering division manager for Water Utilities, described the facility as a regional wastewater treatment plant intended to serve the Clear Creek basin, relieve capacity pressure at Pecan Creek, and reduce proliferation of small developer‑built plants.

Staff said the city received a TCEQ discharge permit for a 10 million‑gallon‑per‑day facility in 2025. The project will include advanced treatment technologies (membrane bioreactor, biological nutrient removal, ultraviolet disinfection), odor control and architectural elements. Estimated construction cost is roughly $455 million; the recommended design contract is approximately 10% of that figure ($45,528,839). Staff outlined a two‑year design schedule followed by approximately four years of construction.

City leaders emphasized minimizing impacts to adjacent mountain‑bike trails and preserving portions of the property for alternate uses; staff proposed rerouting impacted trails and adding educational signage. The contract awards design and phased coordination work (including coordination with a Construction Manager at Risk delivery model) to the selected firm.

Council approved the design contract on a unanimous vote. Staff said alternate funding strategies are being pursued to reduce near‑term rate impacts for utility customers; the action at this meeting authorized the contract execution only, with specific construction funding and schedule to be addressed in future budget actions.