District updates board on capital projects funded by Oracle Ridge sale
Summary
Superintendent Nehrmeyer told the board HVAC units for Building A are installed and that quotes have been received for K–4 carpet replacement (installation planned for June–July), gym lighting, flooring and bathroom improvements funded from the Oracle Ridge sale.
Get email alerts on the Facilities Capital Projects topic
No spam. Unsubscribe anytime.
Superintendent Nehrmeyer briefed the Governing Board on the status of capital projects funded by proceeds from the Oracle Ridge sale. She reported that new HVAC units for Building A have been installed and completed and that the district has received quotes for classroom carpet replacement for kindergarten through fourth grade, with installation expected in June or July.
Nehrmeyer said the district also has quotes for upgrades to gym lighting, gym flooring and gym bathroom improvements. She told the board she will continue to provide monthly updates on project progress as contracts and installation timelines are finalized.
No formal motion to award new contracts was recorded at the Feb. 9 meeting; the board was informed of project status and expected next steps.