Committee approves $2,826.78 change order for traffic control on South 10th Street water‑main work
Summary
The committee approved change order No. 5 for South 10th Street reconstruction to pay $2,826.78 for two traffic‑control mobilizations and device rentals necessitated by a lane closure on County Road 117 during water‑main installation; the cost will be charged to the water enterprise fund.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Paul Sandy presented change order No. 5 for the South 10th Street reconstruction project, explaining a lane closure on County Road 117 (Industrial Park Road) was necessary to install a water main because the road has no shoulders and is part of a truck detour route for the Highway 210 project.
Sandy described coordination with Crow Wing County and said the total traffic‑control cost for two mobilizations (drop‑off and pickup) plus rental and the contractor’s allowed markup totaled $2,826.78. "That total traffic control that was delivered to the site totaled $2,826.78," Sandy said. Staff recommended approval and indicated the water enterprise fund would cover the cost because the water‑main installation drove the need for the lane closure.
A council member asked whether this lane‑closure cost had been anticipated in the original bid; Sandy said the lane closure was not shown in the bid package and therefore was not part of the contractor’s bid. The committee moved, seconded and approved the change order by voice vote.