Summary

City Engineer Margie Pozin updated council on the Rogers Bridge and park phases; discussed temporary median extension at Davenport Road with a possible early traffic signal, at-grade crossings and a quiet zone target; council selected form liner with stain and simple vertical black railing for SR 120 walls.

City Engineer Margie Pozin briefed the council on multiple infrastructure items at the Feb. 27 work session.

Rogers Bridge and associated park Phase I and II projects were updated with schedule and status information; Pozin provided timing context for upcoming work.

On Davenport Road, Pozin said recent discussions with the Georgia Department of Transportation would allow the city to extend the median as a temporary safety measure. She said a traffic signal might be installed earlier than previously expected—potentially in late summer 2023—at-grade crossings could be operational in late 2023 or early 2024, and a railroad quiet zone might be achievable by the second quarter of 2024.

On State Route 120 coordination with GDOT, Pozin presented wall-treatment and handrail options; the council agreed on form liner with stain and simple vertical black railing, with signage and landscaping to be addressed later.

These updates were informational; no formal project bid awards or final approvals were made at the work session.