RSU 67 board reviews summer capital projects: brickwork, gym upgrades, HVAC, vans and outdoor classroom improvements

RSU 67 School Board · June 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board members reviewed a package of summer capital projects including chimney-focused brick repointing, replacement of a failing gym divider with a curtain system (work to start July 20), gym-floor sanding and refinishing (after July 20), intercom upgrades (mid-July), heat-pump installations for office spaces, bids for transport vans, and Bailey Fund–funded outdoor classroom additions and fencing.

The RSU 67 School Board reviewed a slate of capital projects planned for the summer, with staff outlining priorities, schedules and funding sources.

Brickwork and chimney: staff said brick repointing will target problem areas and that a tall chimney at the Albert building is the top priority because of its poor condition.

Intercoms and HVAC: intercom upgrades are scheduled for mid-July once purchase orders are issued. Staff said they will install a 36,000-BTU multi-head heat pump to serve the EPB front offices, replacing inefficient window units; similar office-level heat-pump work was completed at the bus garage to avoid running furnace systems for large thermal mass areas.

Gym divider and floor: the panel divider in the MA gym will be replaced with a modern curtain-style divider to avoid mechanical jamming and safety issues; work was scheduled to begin the Monday after homecoming (July 20). A contracted sanding and refinishing of the MA gym floor will follow, leaving the gym out of service into late summer; staff said summer users have been notified.

Flooring and vehicle procurement: staff plan refinishing work on original junior-high hardwood floors and select hall and library floors from the 1933 section; the equipment fund will support bidding for a 15-passenger van and a used van for special-education transport when funds are available.

Outdoor classroom and Bailey Fund grants: the district received a Bailey Fund grant to add pavilions, picnic tables and interpretive signage for an outdoor classroom; an additional Bailey Fund award will fund a chain-link fence near the junior-high shoreline rocks to reduce maintenance and improve safety during large events. Staff reported consulting a wildlife biologist about geese mitigation; the biologist said vegetation and a shoreline barrier could reduce goose use over decades (estimate given as roughly 30 years).

Fuel depot application status: staff said an application for a used fuel-storage facility is on hold because the specs for the specific tank (sourced from University of Maine/Thorntons) could not be located and the state application requires detailed tank specifications; the project is on the back burner until the proper documentation can be found.

Ending: the board received the updates and will consider any required follow-up actions and purchase orders in subsequent agenda items; no additional formal actions on these capital items were recorded during this update.