Board approves emergency street sweeping and discusses storm surge resilience planning
Summary
Following recent hurricanes, River Ridge supervisors approved a one-time $1,475 emergency street-sweeping contract and discussed a multi-year storm surge resilience plan that may require interagency coordination; Mr. Long described a scenario where a 10'–12' surge could have flooded 45–55% of the community.
Get email alerts on the Storm Resilience topic
No spam. Unsubscribe anytime.
The River Ridge CDD on Oct. 22 took short-term storm‑recovery steps and discussed longer-term resilience planning.
Chair Bob Schultz and Premier Lakes representative Bill Kurth described storm cleanup work; Precision Cleaning, Inc. performed eight loads of debris removal and the board approved a one-time emergency street‑sweeping payment of $1,475 and authorized staff to add week‑to‑week cleanings for the next month if necessary.
Separately, Eric Long outlined a storm surge resilience initiative for Pelican Sound that would include an advisory or review panel and coordination with county, state and federal agencies. Long presented a hypothetical analysis for a storm like 'Hurricane Milton' showing that a 10‑ to 12‑foot storm surge could have flooded an estimated 45%–55% of the community, and he asked the CDD to designate a board and staff representative for coordination; Mr. Long and newly sworn supervisor Keith Merrill were assigned to assist, and Mr. Krebs was authorized to provide technical help as needed.
Mr. Kurth also noted one nano‑bubbler machine will need repair; staff will revisit electrical proposals for relocating aeration equipment that is too close to a homeowner lanai. The board commended staff and contractors for a prompt storm response.