Summary

The county’s Facilities/Maintenance Director reported that the Emergency Operations Center project will include an automatic water shut‑off with three sensors and heat‑pump heating with propane backup; a requisition meeting was scheduled for March 4, 2026.

Dennis Walls, Hancock County’s Facilities and Maintenance Director, updated the commissioners on the Emergency Operations Center (EOC) project at their March 3 meeting.

Walls said a requisition meeting was scheduled for Wednesday, March 4, to advance procurement. He described an automatic emergency water shut‑off system that will detect leaks at three sensor locations, shut the building’s water main if triggered, and send automatic notifications when the shut‑off activates. Walls said the heating design will rely on heat pumps with propane backup.

Commissioner DiBella asked whether any building systems would be water‑dependent while the EOC was vacant; Walls said only a possible ice maker might require water. The that‑was‑the‑extent response indicates the county does not anticipate major continuous water needs during vacancy.

The project is moving into requisition and procurement steps; Walls will attend the March 4 requisition meeting and report progress to the commissioners as procurement advances.