Safford delays some major projects — library annex, fieldhouse and fire station timelines moved
Summary
Council heard staff push the library annex to 2028 to avoid conflicts with a potential fire station site, move the fieldhouse to 2031 pending partnership interest, and shift $4 million in fire station construction costs into 2028 for site selection and design.
Get email alerts on the Project Timing topic
No spam. Unsubscribe anytime.
Staff told the council that several large projects were being rescheduled to reduce risk and allow more design work. Troy Bingham said the library annex — which carries substantial grant funding — is being moved to 2028 because its site may conflict with a potential new fire station; he emphasized the annex remains under consideration but that the timing better matches grant and site decisions.
The planned fieldhouse was shifted to 2031 in the current CIP, with staff noting interest from potential public‑private partners but no firm agreement yet. "We've gotten recent information that there is an interested party," Bingham said, adding the city could revisit the timing if a partner firmizes a plan.
For the fire station, staff moved approximately $4 million of construction costs into 2028 to allow for site selection and architectural renderings that will inform final borrowing amounts. On landfill planning, Public Works Director Lance Henry said a post‑closure and compaction study now pushes the expected fill horizon out to roughly 2047 rather than 2044, while recommending planning for redundancy (a second scale) and equipment protection measures.