Neighbors press for fuller wetland, vernal‑pool and stormwater review at Ferry Road private‑way hearing

Saco Planning Board · June 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Planning Board continued review of a private‑way application at 530 Ferry Road after neighbors and independent peer review flagged potentially unmapped wetlands, recommended an in‑season vernal‑pool survey and asked for a formal stormwater plan; the board scheduled a sitewalk for July 8 and continued the hearing to Aug. 18.

The Planning Board continued the public hearing on a proposal to create a private way off Ferry Road (530 Ferry Road), directing the applicant to provide additional ecological and stormwater information after neighbors and an independent peer reviewer raised concerns about unmapped wetlands and possible vernal‑pool habitat.

Applicant representative Austin Fagan (BH2M) told the board the proposed private way would be under 10,000 square feet of new impervious surface and that the project team had contacted agencies and submitted a self‑verification to the Army Corps of Engineers and an SRCC permit application. Fagan said the design confines road runoff onto the applicant’s property and uses shallow swales and a small conveyance culvert to move water to on‑site wetlands.

Residents urged greater caution. Lauren Harner (540 Ferry Road) cited Normandeau Associates’ peer review that concluded additional wetland areas appear to exist beyond the applicant’s delineation and noted that the peer reviewer recommended an in‑season vernal‑pool survey coordinated with the Maine Department of Inland Fisheries & Wildlife. "Given how close the project appears to be to [the 10,000‑square‑foot threshold] and the unresolved questions regarding wetland boundaries, I believe the board should require a formal stormwater management plan before considering approval," Harner told the board.

Neighbor Lynn Copeland (526 Ferry Road), who lives adjacent to the proposed access, said the road alignment begins at her property line and will bring heavy construction activity immediately adjacent to her historic house; she requested better buffering, clearer demonstration of drainage behavior and assurances about driveway access and winter maintenance.

The board scheduled a sitewalk for 8 a.m. on July 8, 2026 to review grading, proximity to houses and existing wetland indicators and continued the public hearing to Aug. 18, 2026 to allow the applicant and peer reviewers to complete an in‑season vernal‑pool survey, update wetland boundaries if needed, and submit a stormwater plan and vegetation/buffering proposals.

What happens next: The applicant will coordinate on‑site wetland verification, complete the vernal‑pool season survey and submit a stormwater management plan and buffering/landscape mitigation before the board resumes the hearing on Aug. 18.