Chestnut bike spine plans finalized; construction PO issued for Chestnut segment

Bicycle and Pedestrian Advisory Commission (BPAC) · June 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

BPAC heard final plans for the Chestnut urban-spine bikeway: a 2.36-mile corridor with mixed protection types, lane reconfigurations and multiple signalized intersections. Presenters said Chestnut plans are final and a construction purchase order has been cut; Edge Hill work remains roughly 90% complete on a later schedule.

A city presenter described the Chestnut and Edge Hill project plans at BPAC on June 15, focusing on the Chestnut urban-spine bikeway.

The Chestnut segment is roughly 2.36 miles, crosses nine signals and includes a mix of concrete-protected bikeways, painted crossbikes for wayfinding, and lane reconfiguration that generally reduces vehicle lane widths to create protected space. Presenters noted constrained sections where only smaller buffers or flex-post protection fit, and discussed interaction points with WeGo transit stops and the railroad crossing.

The presenter said the Chestnut portion’s plans are final and that a construction purchase order has been cut for that segment; the Edge Hill portion is about 90% complete and on a different timeline. Commissioners and WeGo representatives urged better mechanisms for detailed plan review (for example via a plan subcommittee) because detailed comments on drainage, protection width and intersection design are difficult to make in a one-hour public meeting when plans are displayed on a screen.

The presenter offered to distribute the full plan set for more thorough review and follow up with the commission.