County approves $143,165 design proposal for Highway Department Phase 2
Summary
Murray County approved a $143,165 professional design services proposal from Widseth for Phase 2 of the Highway Department project and discussed timeline targets for design and bid award.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
County staff reviewed proposals for Phase 2 of the highway department build-out and recommended awarding professional design services to Widseth (architects and engineers). Staff compared Widseth’s proposal to a previously discussed $230,000 quote and noted Widseth’s price is lower; the board approved Widseth’s professional-services proposal for $143,165.
Staff and the county engineer (Larry) said the schedule would likely target a mid- to late-October release for construction documents and a tentative November bid award. Commissioners also discussed minor scope items not requiring architect involvement — like installing a flagpole — and agreed those could be procured separately.
On motion and second the board approved the design contract and directed staff to move forward with contracting and timeline coordination.