Board authorizes amendment to Moyock regional wastewater early‑works agreement
Summary
Currituck County authorized an amendment to the design‑build agreement (early works package 2) for the Moyock Regional Wastewater Treatment Plant and delegated signature authority to the county manager; staff said new basins should be usable by late 2026 and options for interim portable capacity are being evaluated.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Currituck County Board of Commissioners authorized an amendment to the design‑build agreement with TA Loving (with Kimley‑Horn as engineer) for the Moyock Regional Wastewater Treatment Plant early‑works package 2 and delegated contract execution to the county manager.
County staff summarized the amendment and the proposal amount included in the meeting packet; the board approved the authorization during the meeting. Staff said the additional basins should be available by late November 2026 and discussed the possibility of adding a portable treatment module to increase interim capacity to up to 200,000 gallons per day if needed.
The amendment is intended to restore and expand local wastewater capacity in the Moyock service area ahead of design and construction of the full treatment plant. County staff noted the project is progressing and that the board’s authorization keeps the schedule moving forward; specific contract details and amounts are included in the packet materials and will be finalized by staff under delegated authority.