Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Municipal Finance topic
No spam. Unsubscribe anytime.
Upland council approves 2025 budget, advances two bond ordinances and extends town manager contract
Summary
The Upland Town Council approved the proposed 2025 budget on Oct. 15, 2024, voted to suspend rules and waive third readings on two bond-related ordinances, accepted a $19,000 contract amendment for lift-station oversight, authorized ARPA payment of $62,385.11 for emergency water-main repairs, and extended the town manager's contract, each by unanimous votes.
Get email alerts on the Municipal Finance topic
No spam. Unsubscribe anytime.
The Upland Town Council on Oct. 15 approved the town’s proposed 2025 budget and took a series of related fiscal and personnel actions during its regular meeting at Upland Town Hall.
Councilman Michael Harbin moved to approve the second reading of the 2025 budget; Heath Slain seconded and the motion passed 5-0. The council also moved, by separate unanimous votes, to advance two bond-related ordinances: Ordinance 14-2024 (bond proceed appropriations) and Ordinance 15-2024 (approval for issuance of a revenue bond). For each ordinance the council approved the second reading and then voted to suspend the rules and waive the third reading, with the associated motions passing 5-0.
Why it matters: the council’s votes cleared the budget for 2025 and moved forward bond authorizations that are tied to the town’s capital and revenue financing plans. Council documents show the council approved the readings and suspensions; the minutes record the votes but do not provide additional fiscal detail about the ultimate bond terms in that text.
Other fiscal and contract actions: Clerk-Treasurer Mary Fletcher presented the September APV register, allowance docket and fund report, which the council approved unanimously. Fletcher also requested payment from ARPA to cover three emergency invoices from Culy’s related to a water-main break at 3rd Street and Berry Avenue and at 3rd Street and McCabe Avenue. The council approved payment of $62,385.11; Fletcher said that payment would leave approximately $75,000 remaining in the ARPA fund.
Town Manager Jonathan Perez presented a recommended amendment to the Kleinpeter contract for additional oversight of the Lift Station project. The amendment would add $19,000 to Kleinpeter’s fee, to be paid from the WW SRF loan. Brad Yordy moved to accept the amendment; Michael Harbin seconded and the motion passed 5-0.
On personnel, Michael Harbin moved to extend a contract to Town Manager Jonathan Perez; Heath Slain seconded and the motion passed 5-0. Council members said they will prepare an updated contract to present to Perez.
Votes at a glance: - Approve second reading of 2025 budget — motion: Michael Harbin; second: Heath Slain; vote: 5-0 (approved). - Approve minutes of Oct. 1, 2024 meeting — motion: Brad Yordy; second: Amy McCrea; vote: 5-0 (approved). - Approve September APV register and fund reports — motion: Heath Slain; second: Michael Harbin; vote: 5-0 (approved). - Approve ARPA payment to Culy's, $62,385.11 — motion: Amy McCrea; second: Heath Slain; vote: 5-0 (approved). - Approve Kleinpeter contract amendment, +$19,000 (WW SRF loan) — motion: Brad Yordy; second: Michael Harbin; vote: 5-0 (approved). - Approve second reading of Ordinance 14-2024 (bond proceed appropriations) and suspend rules to waive third reading — motions: Michael Harbin; Brad Yordy; vote: 5-0 (both motions approved). - Approve second reading of Ordinance 15-2024 (revenue bond) and suspend rules to waive third reading — motions: Heath Slain; Michael Harbin; vote: 5-0 (both motions approved).
What’s next: Town staff said Commonwealth will provide a project update at the next meeting. The council did not provide additional detail in the minutes about final bond terms or closing timelines. The council’s next regular meeting is scheduled for Nov. 19, 2024, at 7 p.m. at Upland Town Hall.