Board approves electrical and restroom repairs; pool contractor says inspection, heating and flooring work expected to finish next week
Summary
The board authorized a $21,825 transformer installation contract with North Electric and approved $7,426 in emergency restroom repairs. A public update said the pool contractor expects health-department inspection Thursday and possible completion by next week.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Southwestern School Board approved contracts and repairs for district facilities and heard a project update on the pool.
Electrical: Administrators presented two quotes to replace an aging transformer and three disconnects tied to the elementary kitchen. North Electric quoted $21,825 and Miller Electric quoted about $25,207.88. North Electric had provided temporary emergency repairs earlier and the board awarded the work to North Electric following discussion about the concrete pad and whether additional work would be needed. A board member moved and the board approved the North Electric bid.
Restroom repairs: The board approved an urgent repair of multiple stalls in the girls’ restroom in the high school gym. Aspire Industries quoted $7,426 to replace a major sewer trunk line component and to restore restroom function; administration said the vendor could perform the work over the Christmas break and that payment will be charged to 2025 operations. The board authorized proceeding to avoid further disruption of public and school use.
Pool update: A public commenter with onsite project knowledge said ALD is on site (on-site supervisor Seth; project manager Kevin Durst) and that the contractor calibrated the Kimroller pool-chemical system and expects continuous operation while finishing painting and installing flooring. The commenter said a health-department inspection is scheduled for Thursday and, "after that happened...our pool has been running non-stop and will continue to run non-stop barring any issues." He added that if everything goes well students could use the pool as early as next week and that a hot-water delivery speed issue remains under review; the board of health reportedly will not delay inspection so long as a plan is in place to address hot-water speed.
Why it matters: The repairs restore essential building services (kitchen power and public restrooms) and the pool progress affects student programming and community use; the board authorized immediate work to avoid service interruptions and to meet inspection timelines.
Next steps: Administration will confirm final contract terms with North Electric and oversee Aspire’s restroom repairs over the break; pool staff will coordinate painting, matting installation and the health-department inspection.