Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Hicksville updates valve replacement progress; Water/Sewer Committee discusses 2025 rate increase and sidewalk fee
Summary
Administrator reported 2 of 6 valves completed by JDY Excavating with a June 30, 2025 completion target. The Water/Sewer Committee discussed proposed 2025 rate increases and a possible monthly sidewalk payment; no decisions were recorded.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Administrator Cory Wann updated council that the 2024 valve replacement project, contracted to JDY Excavating, has completed two of six valves and expects substantial completion by June 30, 2025. Four valves remain to be replaced.
Council heard that the Water/Sewer Committee met Sept. 23 and discussed proposed rate increases for 2025 and a proposal to institute a monthly sidewalk payment on utility bills. The committee’s minutes were included in council packets and staff signaled ongoing discussion; no rate changes or billing changes were approved at the Oct. 7 meeting.
The Finance Committee also convened Oct. 1 to begin 2025 budget discussions and will meet weekly until outstanding issues are resolved.
