Building inspector given discretion to issue Temporary CO for Rivera Toyota as site nears completion

Planning Board of the Village/Town of Mount Kisco · May 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Rivera Toyota at 227 Kisco Avenue reported 90% site work complete and 99% of inspections finished; the Planning Board voted 6–0 to allow the Building Inspector discretion to issue a Temporary Certificate of Occupancy, pending consultant confirmation of outstanding items.

Representatives for Rivera Toyota told the Mount Kisco Planning Board on May 13 that about 90% of site work is complete and that 99% of required inspections for the project have been completed. Anthony Rizzo Carnivala and a member of the construction management team identified as Ms. Russell provided the update to the board.

Building Inspector Peter J. Miley said items remaining to be confirmed include relocation or removal of a dumpster (placement outside the rear of the building would require a variance) and fire‑safety items. Village consultants will conduct a site inspection to confirm outstanding items.

Michael McGuirk moved to give the Building Inspector discretion to issue a Temporary Certificate of Occupancy; Crystal Pickard seconded and the motion carried 6–0.

The minutes do not record a deadline for final completion or detailed conditions attached to the temporary certificate; the building inspector was authorized to act at his discretion pending confirmation of outstanding items.