Sweetser withholds retainage on CCMG street project over DeVoe Drive pavement dispute; contractor deadline set on separate project
Summary
The council is withholding retainage on the CCMG 2023-2 Street Project because of an unresolved pavement issue on DeVoe Drive, preventing project closeout and new CCMG applications; the contractor E & B must finish CCMG 2024-1 by May 5, 2025, or face a $1,000-per-day fine.
Get email alerts on the Infrastructure Dispute topic
No spam. Unsubscribe anytime.
At its Feb. 27 meeting the Sweetser Town Council discussed continuing problems on the CCMG 2023-2 Street Project related to a pavement defect on DeVoe Drive. Council members said the town is withholding retainage from the contractor pending a final determination of who is responsible for the defect; the project cannot be closed out while retainage remains withheld, and the town is ineligible to apply for future CCMG grants until the matter is resolved.
Jason (staff member) reported that the separate CCMG 2024-1 project, contracted to E & B, has a completion deadline of May 5, 2025, and that the contract includes a stated liquidated-damage provision of $1,000 per day for delays beyond that date. Council discussion focused on communicating with the contractor and engineer—identified in the minutes as USI (engineer) and Brooks (contractor) for the earlier project—to determine the origin of the DeVoe Drive pavement issue before releasing retainage.
The council tabled the retainage matter pending a final determination of fault. No vote to release funds or close the project occurred at the meeting. Council members noted that the unresolved issue affects the town’s ability to apply for new CCMG projects while the current project remains open.
Next steps recorded include staff follow-up with the engineer and contractor to resolve the DeVoe Drive issue and monitoring E & B’s progress on the CCMG 2024-1 project ahead of the May 5 deadline.