Lower Pottsgrove awards contracts for new municipal building totaling $5.08 million
Summary
The Board unanimously approved contracts for a new municipal building, awarding four major contracts with combined base bids totaling about $5.08 million; commissioners said value engineering and separate bidding for a generator could lower final costs.
Get email alerts on the Municipal Building topic
No spam. Unsubscribe anytime.
Lower Pottsgrove Township on Dec. 2 unanimously awarded the major construction contracts for a new municipal building, approving four bids that together total about $5,077,680.
The Board of Commissioners voted 5‑0 to award: a general‑contractor contract to Balton Construction (base bid not to exceed $3,200,000); an HVAC/mechanical contract to Integrity Mechanical (base bid not to exceed $735,000, subject to post‑bid value engineering); an electrical contract to Hard Hat Services (total after accepted alternate $664,189.82); and a plumbing contract to Hirschberg Mechanical (base bid $478,490). Commissioner Michael McGroarty made the motions to award the contracts; Commissioner Robert Mohollen seconded the motions.
Manager Edward C. Wagner and the project's owner's representative, Chris Caggiano, told the board that one accepted contract alternate reduced the size/cost of a generator and that the Township plans to bid the generator separately to get a lower price. An alternate to replace four attic windows (about $36,299) was declined on the architect's recommendation.
Commissioners framed the awards as the next step to begin construction. Commissioner Robert Mohollen, discussing the Township's overall capital posture, said the Capital Reserve Fund is “fully funded” and that he “foresees no problems and no tax increases for the upcoming year.”
The Board also authorized staff to solicit proposals for on‑road and off‑road diesel fuel and approved the 2025 meeting dates; both motions passed unanimously.
Votes at a glance - Balton Construction (general contractor): approved 5‑0; motion by Commissioner Michael McGroarty, second by Commissioner Robert Mohollen. Base bid not to exceed $3,200,000; Alternate G‑01 (attic windows) declined. - Integrity Mechanical (HVAC/mechanical): approved 5‑0; base bid not to exceed $735,000; anticipated value engineering post‑bid. - Hard Hat Services (electrical): approved 5‑0; base bid $797,389.82 with Accepted Alternate E‑01 (generator reduction) producing total $664,189.82. - Hirschberg Mechanical (plumbing): approved 5‑0; base bid $478,490. - Authorization to request diesel fuel proposals: approved 5‑0. - 2025 meeting dates advertisement: approved 5‑0.
What happens next Contract documents and post‑bid value engineering steps will be completed before final contract execution and construction mobilization. The Board stated it expects construction to begin once the contractual and permitting steps are finished.
Provenance This article is based on the Board's discussion and motions in SEG 005–SEG 006. Evidence includes the motions recorded by the Township Manager and roll‑call vote statements awarding the four contracts.