Board hears DPW renovation progress, Marcus Christ Hall redesign and 300 S 12th St. grant update
Summary
Trustees received updates on the DPW renovation (demolition completed, foundations poured, structural work ongoing), heard that Marcus Christ Hall design costs exceeded estimates prompting a reduced footprint and potential bonding, and were told the village expects state grant news Sept. 20 on 300 S 12th St. with remediation and park development next steps.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Village of New Hyde Park Board of Trustees devoted a significant portion of its Sept. 19 meeting to capital projects and infrastructure updates.
Department of Public Works Superintendent Igor Sikiric said the DPW renovation, two months into work, has completed demolition of parts of the garage, salt shed, office trailer and storage building; contractors have poured the foundation for a new truck garage and recyclables transfer area and are performing structural and electrical repairs. "It is currently anticipated that the majority of the structural work which consists of a new truck garage, new office, and new salt shed should be completed by the end of the year," Sikiric said.
On facilities planning, board members addressed the Marcus Christ Hall project after receiving an updated design estimate that exceeded the approximately $2.5 million the village had budgeted. The board reviewed value-engineering options and reduced the building footprint from about 5,000 square feet to 4,400 square feet to lower costs. Mayor Christopher Devane said the village may seek bonding to cover remaining costs and could delay some street repairs to free funds; the board said it expects an updated design and estimate in early October and hopes to go to bid later in the fall.
The board also discussed 300 S 12th Street. Mayor Devane said village officials expected word from the state on Sept. 20 about a grant disbursement agreement for that property. He said there are remediation issues with an old sock factory and a house on the site; the village expects a remediation credit and plans to repave, install a dry well and develop parking and park space. "As soon as those two areas are done, we will start to develop the park; need to do those areas first so we don’t impact our residents' parking area," Devane said, and the board anticipates 70–75% of the park complete by Thanksgiving, subject to remediation and funding timelines.
Trustee Rainer Burger provided additional infrastructure updates, including the conclusion of most third-track LIRR work and newly installed signage, and Water Authority projects such as ordering a reactor for Well 57A (currently operating at 73%) with delivery planned for mid-December. Board members flagged a contractor dispute delaying Station 44 work and a halted Tank 20 rehabilitation project for which a claim against the contractor’s performance bond has been submitted.
Why this matters: the DPW renovation and other capital projects affect public works capacity, service delivery and local construction schedules; the Marcus Christ Hall decision will determine facility size and debt choices; and the 300 S 12th Street grant and remediation timeline directly influence when park and parking improvements can proceed.
The board directed staff to continue design refinements, prepare for potential bonding and keep residents informed about timelines as bids and remediation progress. No new formal votes on the capital items were recorded at the meeting; the board signaled further action pending updated cost estimates and state grant confirmation.