Vernon Center tables well-project award after bids exceed estimates; USDA-RD funding review required
Summary
The council held off awarding a contract for water and wastewater plant improvements after two bids exceeded engineering estimates; the low bid from Rubin Construction was $1,216,310 and the council asked USDA Rural Development to reconcile loan offsets before proceeding.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
The Vernon Center City Council decided not to award a contract for planned water treatment plant and wastewater improvements after bids came in above the engineer’s estimate.
Engineer Chris Knutson said two bids were received at a July 29 bid opening; the low bid from Rubin Construction of Tyler, Minn., was $1,216,310. Knutson and Clerk Kara Hansen said both bids exceeded the engineer’s projected amounts, and USDA Rural Development staff indicated the city must reconcile prior loans and offsets — including amounts tied to a Northland Trust loan and two PFA loans — before RD can confirm how much of the RD loan remains available for the well project.
Hansen summarized figures used earlier in the year: a combined figure for sewer and water that RD had provided for loan calculations, and a working number of approximately $1,364,000 that had been adjusted to $1,260,978 for the June 2026 milestone. She said Ed Gilmore of USDA-RD must calculate what the city owes on prior loans and how remaining RD funds can be applied to the well project. The council agreed it could approve a bid contingent on RD concurrence but should not issue a notice to award until RD confirms funding; if RD later confirms funds, the council may call a special meeting to formally approve an award and notice to award.
Councilors approved Pay Application #16 (pending receipt of bonding and other outside funds) and MRWA invoice #11 as separate items, while leaving the well contract decision dependent on USDA-RD’s determination.
Engineer Knutson also noted warranty items from the larger infrastructure project — including popped concrete and unglued cleanouts — that contractors must remedy under warranty.