Vernon Center council directs staff to draft WWTP/WTP project list to meet USDA-RD funding match

Vernon Center City Council · February 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Mayor Dana Ziegler and city staff were told they must identify roughly $210,000 in wastewater-treatment projects and $475,000 in water-treatment projects to qualify for full USDA-RD funding; engineers and the public works supervisor were asked to produce cost estimates for review at the March meeting.

Vernon Center Mayor Dana Ziegler told the city council that a recent meeting with USDA Rural Development officials showed the city must identify about $210,000 in wastewater treatment plant (WWTP) projects and $475,000 in water treatment plant (WTP) projects to meet a required 50/50 funding split for full loan/grant support.

Engineer Chris Knutson and Public Works Supervisor Mark Willette discussed potential work that could be included. Knutson said a new well is a possibility but estimated it could cost the city roughly $500,000 and would require a separate bid as it would not qualify as a change order to an existing contract. Willette identified immediate needs at the WWTP including new blowers, HVAC work, and electrical upgrades; he also said silencers at the plant appear plugged and that he will circulate pricing on replacements.

The council discussed schedule implications. Knutson said preparing bidding documents would take a month or two, with another 45–60 days for funding approvals; depending on timing, well work could proceed in winter months. Willette noted that if project funds remain after primary work, the city could apply remaining funds toward a jetter, although buying a jetter could also be financed through bonding.

Mayor Ziegler instructed Knutson and Willette to draft a prioritized list of projects and cost estimates for council review at the March 4 meeting so the city can submit a package to USDA-RD. The council did not take a formal vote on any specific construction contract at the meeting; the action was a direction to staff and consultants to prepare documentation.