Skyline City Council approves $71,686.67 Wellhouse payment and $9,419 change order
Summary
The Skyline City Council unanimously approved a $71,686.67 payment to WEB Construction for the Wellhouse Project and authorized Change Order No. 4, adding an exterior shut-off valve that will cost $9,419 and extending completion to Nov. 15.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Skyline City Council on Sept. 9 unanimously approved payment request No. 9 for the Wellhouse Project, releasing $71,686.67 to WEB Construction.
Bryan Petzel of ISG explained the related Change Order No. 4, which adds an exterior shut-off valve at a cost of $9,419 and requests an extension of the work-completion date to Nov. 15. "The cost of the exterior shut-off valve will be $9,419," Petzel said. Michelle Kotila moved to approve payment to WEB Construction; Shirley Piepho seconded. The motion passed unanimously.
The council’s action follows the treasurer’s report showing a Water Tower/Pump House project fund balance of $427,881.84, which the council noted when considering project payments. Council members did not debate alternative contractors or additional contingency funding at the meeting.
Next steps: the contractor will proceed under the amended schedule through Nov. 15, and council staff will process the payment paperwork.