Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Contract Extension topic
No spam. Unsubscribe anytime.
Committee extends electrical contract to finish generator work at Countryside
Summary
The Public Works Committee approved a short contract extension so a contractor that began generator work at Countryside can finish under the older term agreement; future electrical work will follow the new contract terms.
Get email alerts on the Contract Extension topic
No spam. Unsubscribe anytime.
The Warren County Public Works Committee authorized an extension of an existing electrical term contract so a contractor that began generator and related electrical work at the Countryside facility can finish that project.
Staff explained the county had a multi‑year term agreement (covering 2022–2025) that expired in April; while a new contract has been awarded for future work, the vendor that started the generator work at Countryside did not win the new bid and the county opted to extend the older contract solely to allow completion of the ongoing project. Future electrical equipment and projects will be handled under the new contract terms.
The committee moved, seconded and approved the limited extension by voice vote; the transcript records committee members saying 'Aye' and the chair declaring the motion carried. The transcript does not record the names of the mover and seconder or a roll‑call tally.

