Council approves time extension for Mountaintops water improvements; staff says no budget increase

City Council · November 19, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved extending the Mountaintops water system improvements project from 210 to up to 360 days after rebidding; staff said the extension covers lost time from rebidding and involves no increase in contract dollars.

The City Council approved a request to extend the construction schedule for the Mountaintops water system improvements project.

Staff explained that when the project was first bid only one company responded at a price nearly $2 million higher than expected; the project was rebid and the rebidding process cost roughly two months. To accommodate the delay, the contractor asked to extend the completion window from 210 days to up to 360 days. Staff recommended approving the extension with no change to the contract amount.

Council moved, seconded and approved the time extension in a roll-call vote. Staff said the project is scheduled to start in January and the additional time would be added to the end of the schedule; no additional funds were requested.

The motion passed and the council recorded yes votes during the roll call.