A clerk read seven bids for a construction project during a public bid opening, recording base bid totals, unit prices, addendums and completion timelines; staff said it will verify documents and return with a recommendation for the low bidder.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
A clerk read seven bids for a local construction contract during a public bid opening and said staff will verify documents and recommend the low bidder after reviewing all parameters.
The clerk opened bids from Probst Builders, Five Oaks Associates, Berslois Construction, GPH Builders, Reinhardt Construction, Little Dixie Construction and Wright Construction, noting that each submission included addendums 1 through 3 and a bid bond. "Generally speaking, it's going to be the low, but we always look at all the parameters before a decision is given," the clerk said.
The bids were recorded in the transcript as follows (base bid amounts as read aloud): Probst Builders — "$2,000,000 960,000 dollars" (no alternates; unit prices: #1 $300/cu yd; #2 $150/cu yd; #3 $150/cu yd; 390 calendar days); Five Oaks Associates — "2,000,000 770,400" (no alternates; unit prices: #1 $210/cu yd; #2 $80/cu yd; #3 $80/cu yd; 365 calendar days); Berslois Construction — $2,620,800 (no alternates; unit prices: #1 $160; #2 $83; #3 $72; 320 calendar days); GPH Builders — $2,798,000 with a voluntary alternate deduct of $75,000 to use Red Dot Building Systems (unit prices: #1 $232/cu yd; #2 $105; #3 $105; 240 calendar days); Reinhardt Construction — $2,763,500 (no alternates; unit prices: #1 $256; #2 $100; #3 $100; 330 calendar days); Little Dixie Construction — $2,889,707 (no alternates; unit prices: #1 $232; #2 $109; #3 $109; 330 calendar days); Wright Construction — $2,727,000 (no alternates; unit prices: #1 $155; #2 $85; #3 $85; 285 calendar days).
The clerk and a staff member noted that subconsultant contact information and compliance documents will be emailed to the file for review. The clerk said the submissions will be compiled and typed up and staff will meet again to make a recommendation for award based on the full review of bids and supporting documentation.
No formal motion or vote occurred during the reading. The next procedural step, as stated by the clerk, is administrative review and a subsequent recommendation to the awarding authority.