Planning board schedules Gulf Cave golf-simulator special permit for May 7 amid ADA, egress and noise questions

Town of Greenburgh Planning Board · April 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Gulf Cave, an 8,000-square-foot indoor golf-simulator operator, was added to the May 7 public-hearing calendar. The board and building department raised questions about ADA access to a mezzanine, a required second means of egress, HVAC upgrades, and noise mitigation; the applicant promised follow-up with the building inspector.

The Planning Board on April 21 set a public hearing for Gulf Cave, a proposed indoor golf-simulator facility converting an old movie theater into approximately 8,000 square feet of simulator bays and a small members'lounge mezzanine.

Attorney Matt Barrons, representing Gulf Cave, said the proposal requires a special-use permit because the interior space exceeds 5,000 square feet. Co-owner Nick Altiero described the operation as a primarily appointment-based, member-forward facility with about eight simulator bays and a mezzanine lounge that would be used by members; he emphasized there would be no food or alcohol service. "We are the first New York location," Altiero said, and he described a member model with hourly bookings and occasional pro instruction.

Board and building-department questions focused on code and accessibility. Staff and several board members cited the building inspector's memo on mezzanine use and accessibility: if the mezzanine cannot be made ADA-accessible, the applicant must provide a comparable accessible space on the main floor or otherwise meet code requirements. Board members also flagged the possibility the mezzanine could need a second means of egress or otherwise be restricted depending on occupancy calculations and New York State code.

Applicants said they had submitted responses to the building-department comments and would recirculate their response memo and updated documents for the building inspector's review. The applicant presented photos and peak-time parking observations and said the landlord manages a large adjacent lot that appears to have available spaces during peak times; staff said it will review circulation and parking evidence as part of the application.

Noise mitigation was discussed; the applicant said interior soundproofing and insulation would be installed between simulator bays and in the ceiling and that the building inspector would review any exterior-noise concerns. Staff asked the Gulf Cave team to discuss the proposed mechanical upgrades (including mini-splits and condenser locations) with the building inspector and to confirm rooftop or rear-yard condenser placement will not create stormwater or operational impacts.

The board set the public hearing for May 7, 2025, and instructed staff to circulate building-department responses and to follow up on outstanding questions about ADA access, egress, and potential liquor-service implications.