Council hears update on State Route 20 utility relocation; GDOT let date pushed to 2026
Summary
The council received a Public Utilities update that second-submission utility plans for the State Route 20 project were submitted to GDOT, a utility-aid request was filed, and the earliest project let date is now expected in July 2026; councilors noted rising cost estimates and that Main Street rerouting is only an idea under discussion.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
At the Loganville City Council meeting on June 12, Councilmember Bill Deval reported progress on the State Route 20 project, saying city staff and contractors submitted second-submission utility plans to GDOT and provided a request for utility-aid. Deval said the project’s "let" date has shifted and is now expected around July 2026.
Deval and other staff described the scope of work as large and costly; one speaker referenced an earlier 2017 estimate of about $2 million and said the most recent estimate he had seen was about $6 million. Deval said the city has completed required plan submissions and will continue preparing project materials so the work is "shelf ready" for GDOT funding to become available.
Councilmembers clarified that the idea of rerouting Main Street to divert big trucks is only an idea presented to GDOT and is not a decided action. Staff said they will keep project partners updated and will continue work on plans and utility coordination while awaiting available state funding.
Next steps: Staff will continue plan preparation and coordination with GDOT; the transcript records no new local funding commitments or final contractor awards at this meeting.