Middletown delays release of contractor retainage as stormsewer punch list remains
Summary
Engineers told the Middletown Town Council that two property releases remain before the 5th Street Stormsewer Project can be closed; the council asked engineers to draft a letter to contractor 3D Company and said liquidation damages may be deducted from retainage.
Get email alerts on the Infrastructure Stormwater topic
No spam. Unsubscribe anytime.
Jeremy Books and Matt Spidel of engineering firm Butler-Fairman-Seufert updated the Middletown Town Council on Oct. 13 on the status of the 5th Street Stormsewer Project, saying only two property releases remain before the contractor can complete the final punch list.
Books told the council the town could assess liquidation damages against contractor 3D Company before releasing retainage if the punch-list items are not completed. Council President Betty Riley asked the engineers to draft a letter to 3D informing the company that the town will wait for completion of the punch list before releasing retainage and that liquidation damages will be deducted, and the town attorney said he would review the letter before it is mailed.
No formal vote was recorded in the minutes; the record shows the council gave direction to staff and consultants rather than taking a formal motion on the retainage release. The minutes note that only two property releases remain as the condition to finish the contractor’s final punch list and finalize the project closeout.
The action leaves the contractor’s retainage withheld pending completion of contract requirements and any deductions the town may assess for delays or damages. The meeting adjourned after other announcements.