Parks director says Riverview Park phase one design, permits on track amid funding worries

City Council (Parks & Recreation) · June 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Parks & Recreation Director Richard Blake told the council Riverview Park’s phase one design and permits are targeted for completion by Sept. 1 with construction possible in October, but council members and residents raised concerns that an upcoming property-tax amendment could jeopardize local maintenance budgets and the city’s ability to sustain parks if funding is reduced.

Parks and Recreation Director Richard Blake told the council the Riverview Park planning effort is “moving along very well,” with permits and a final phase-one design targeted by Sept. 1 and construction timing “imagined” to begin around Oct. 1. The phase-one work he described includes dredging and shoreline stabilization at the Main Street boat ramp, upland stabilization, parking upgrades to better accommodate boat trailers, and replacement or relocation of the splash pad and playground equipment.

The update came during a long discussion about whether to proceed with major park upgrades before a November property-tax amendment that several council members said has created substantial local uncertainty. “I’ve talked to a lot of people,” a committee member said, urging caution: if the amendment passes and reduces property-tax revenue, the city could face hard choices about maintaining more than 20 parks.

Blake said the project relies on a mix of grant funds and a discretionary sales-tax match; he stressed that discretionary sales tax is restricted to certain infrastructure uses and that some grant funds (he cited Florida Inland Navigational District awards) are not affected by property-tax changes. He warned that some facilities are already at or near failure: “the splash pad...has been down for 10 days...it’s over 20 years old,” Blake said, arguing that deferral of repairs risks forced closures that would increase operating pressures.

Council members and staff also discussed outreach: staff plan public input through on-site events and an online survey (designed with a form tool) so residents can choose among conceptual designs rather than delve into detailed engineering. The council noted social-media commentary and anonymous online feedback have limited value, and members urged more in-person engagement.

No formal vote was taken on the Riverview project in the meeting. The council approved minutes from its April 27 meeting earlier in the session (a motion was seconded by Mr. Holland); the transcript does not record a numerical vote tally for that action.

The next steps, as staff described them, are public engagement on the conceptual splash-pad and playground options, completion of permitting and final phase-one design by early September, and subsequent manufacturer customizations once a preferred concept is chosen. Staff emphasized that some elements (for example, splash-pad replacement and critical playground repairs) are intended to address immediate safety and inspection issues rather than add new amenities.