Hogansville council recommends faster contractor to repair Tower Trail boardwalk
Summary
Hogansville councilors favored Right Angle Roofing’s $48,500 quote to rebuild the Tower Trail outdoor classroom and boardwalk despite a slightly higher price than a competing $45,500 bid, citing a substantially quicker start and completion window; the recommendation will go to the Regular Meeting for formal approval and to be funded from SPLOST parks dollars.
Get email alerts on the Boardwalk Repair topic
No spam. Unsubscribe anytime.
Mayor Jake Ayers convened the Hogansville work session on Sept. 2, 2025, where councilors reviewed two contractor bids to repair and reopen the Tower Trail outdoor classroom and boardwalk, which is currently closed and considered a liability.
Council materials show Principal Construction submitted a $45,500 bid to rebuild benches, decking and joists; that bid did not include pressure washing and sealing and the firm would need three to four weeks before starting. Right Angle Roofing’s revised verbal total is $48,500 after removing an item for pressure washing and sealing; the firm told the city it can begin next week and estimates two to three weeks for completion. For about $3,000 more, councilors noted the faster schedule would likely return the boardwalk to public use sooner — potentially before the Hummingbird Festival — and the group favored the faster option.
The council directed staff to place the recommendation on the Regular Meeting agenda for formal approval and to fund the work from SPLOST dollars allocated to Parks, Recreation and Trails. The work session record does not show a formal motion or vote; formal contract award is expected at the Regular Meeting.
City staff noted the project will require a generator and scaffolding because equipment cannot be brought directly onto the site, which complicates logistics and contributed to the higher contractor estimates. The minutes do not specify a contract start date beyond the contractor-provided windows or identify contingency details such as pressure-washing scope or warranty terms.
The work session adjourned at 6:44 p.m.; the boardwalk item will appear on the Regular Meeting agenda for a final vote.