During the capital‑plan presentation, staff laid out options to renovate the aging School Support Center (MEP repairs, envelope upgrades, full rebuild, or relocate/sell). Board members debated costs, timing, geographic tradeoffs and asked staff to return with costed options; one member proposed an RFQ to test a solar parking canopy pilot.
Get email alerts on the Capital Plan topic
No spam. Unsubscribe anytime.
District capital staff presented a preliminary five‑year capital plan and a set of options for the School Support Center (SSC) during the June 23 workshop, and the board spent significant time weighing whether to invest in major mechanical, electrical and plumbing (MEP) repairs or pursue demolition and rebuilding (either on the existing site or at another district property such as PSC or Wakeland).
Clark, the facilities presenter, explained three packaged options for the SSC: an MEP‑focused renovation (option 1, roughly $17–18 million), exterior envelope repairs and window upgrades (option 2 portions priced at ~$3 million), and an interior reconfiguration estimate (another ~$6 million); a full combined renovation was estimated near $27 million. Staff also shared higher‑level estimates for demolish/rebuild on site and for building at alternate district properties (each roughly in the low $40 million range) and noted a potential sale of the current site could offset part of the cost (staff used a placeholder of about $11 million).
Board members noted the SSC has required repeated repairs (Clark and staff reported roughly $2.5 million in major repairs over recent years) and raised concerns about continued patching versus the lifecycle cost of a new facility. "If we pour $17–18 million into mechanical systems but the envelope is leaking, we may continue to spend later," a board member said, pushing for combined envelope and MEP work if the board opts to renovate rather than relocate.
Members also debated location and access. Some favored keeping the district's central downtown property for long‑term value and public access; others preferred building at PSC or Wakeland for operational consolidation and parking. Several board members asked staff to return with 'option 4' variants that would combine partial interior reconfiguration with necessary MEP/envelope improvements and a clear funding path for each scenario.
On renewable energy, a board member proposed a pilot study and an RFQ to explore a solar parking canopy at the SSC site (or future site). Proponents said solar can yield shade and on‑site generation and suggested a modest pilot to gauge feasibility and payback; staff agreed to research costs, local district examples, and potential vendors and return with findings before advancing procurement.
No formal action or vote occurred; board direction was to have staff bring back refined cost estimates, funding options and feasibility information (including solar pilot research) for further consideration before finalizing capital budget allocations.