Council sets assessment hearing for 10th Street project and awards water‑main contract
Summary
Council adopted resolutions to prepare the final assessment roll and set a September hearing for the 10th Street Southwest project, then awarded a construction contract to Drestle Contracting for $341,996.14 and approved $29,000 in engineering construction services for inspection and administration.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
City staff asked the council to order preparation of the final assessment roll for the 10th Street Southwest project and to set a public assessment hearing for the September meeting. Council adopted the two resolutions on a roll call vote (Gina: yes; Dave: no; Kyle: yes).
Staff also reported nine bids were received for the related street and water work; the low bidder was Drestle Contracting of Shago City at $341,996.14. Council voted to award the construction contract to Drestle and later approved a separate engineering and construction‑administration agreement for $29,000 to provide construction inspection and project administration.
Staff described the construction plan as mostly trenchless pipe installation across a wet area with short open cuts at connection points; they said the contractor expects to begin work in September with completion in October/November under current scheduling. Council discussed notification to affected residents and the potential for brief water service interruptions when crews make tie‑ins. Staff agreed to provide at least door‑to‑door notices and to coordinate flushing to minimize staining issues after new connections are opened.
Councilmembers raised the low bid difference and asked about potential for overruns; staff and the city engineer said the project is modest in scale and the low bid likely reflects contractor workload and pricing rather than a systemic problem, and that contingency and inspection provisions remain in place.
Next steps: staff will finalize contract paperwork with Drestle Contracting, issue notices to affected residents ahead of any scheduled shutoffs, and proceed with the engineering services agreement for construction administration.