Northfield authorizes design-builder agreement with S&S Interiors for police and administration buildings

Village of Northfield Regular Council · June 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a Standard AIA Owner and Design-Builder Agreement with S&S Interiors for Phase 1A of a new police building — a one-story, up to 4,130 sq. ft. facility with a not-to-exceed cost of $1,296,200 — and authorized design work for future phases; council also approved $55,000 in additional design/contract-administration funds.

The Village of Northfield Council voted Oct. 23 to authorize the mayor to enter into a Standard AIA Owner and Design-Builder Agreement with S&S Interiors, Inc. to construct Phase 1A of a new police department building and to design subsequent phases, council minutes show.

Law Director Brad Bryan read the ordinance by title and Engineer Daniel Collins distributed site-plan documents to council. Collins described Phase 1A as a one-story building of up to 4,130 square feet with a not-to-exceed cost of $1,296,200. The legislation also authorized an additional $55,000 for design and contract-administration work covering all phases; the minutes note $17,250 of that amount has already been paid.

Councilmember Alan Hipps moved to suspend the three-reading rule; Councilmember Renell Noack seconded the motion, which passed on a roll-call vote. Hipps then moved to adopt the agreement authorization and Noack seconded; the resolution was approved on a roll-call vote with Councilmembers Ferko, Noack, Magistrelli and Hipps voting yes.

Council minutes state that approval for Project Phases 1B (an addition to the police building) and 2 (a new administration building) will be requested after completion of Phase 1A. Estimated sizes and costs recorded in the minutes: Phase 1B up to 4,570 sq. ft., estimated at $1,320,000; Phase 2 up to 3,400 sq. ft., estimated at $969,000. The council took no floor amendments to the design agreement during the meeting.