Eveleth council tables decision on Phase 3A parking project at Fail Pond pending grant extension
Summary
At its May 19 meeting the Eveleth City Council voted to table awarding a contract for Phase 3A of the Fail Pond parking project while staff seeks a possible one-year grant extension; staff presented options to reduce scope and cost but members preferred to await funding clarity.
Get email alerts on the Infrastructure Parking topic
No spam. Unsubscribe anytime.
EVELETH, Minn. — The Eveleth City Council on May 19 tabled action on awarding a contractor for Phase 3A of the Fail Pond parking-area project while staff checks whether the city's grant can be extended for another year.
Allan, a city staff member who presented the bid information, said removing the concrete portion of the project would cut roughly $20,000 from the contractor's base bid, bringing that figure to about $76,555. He also described a total project estimate of roughly $92,000 (including alternates and related costs). Councilors and staff discussed whether the city could obtain a one-year extension on the grant that is intended to cover part of the project cost.
"If we did take out the concrete scope ... that would be roughly a $20,000 decrease," Allan said, citing the lower base-bid figure. Jerry (city staff) told the council he expected the granting agency would often allow a one-year extension but warned there was no guarantee a larger award would be available if the city re-applied.
Council discussion focused on balancing the desire to complete the parking work against committee members' concern about budget shortfalls and preserving the option to pursue a higher-quality "deluxe" scope next year. Councilor Lilis said he supported delaying the work if an extension is available to allow the city to budget and potentially secure a better price.
After debate, a motion to table the item contingent on confirming a grant extension carried by voice vote. Staff was directed to check with the granting agency and return the item to council once the extension status is confirmed.
Why it matters: The parcel around Fail Pond is part of a broader trails and park-area plan; changes to scope and timing will affect when parking improvements and trail connections are completed and how much the city must contribute from local funds.
What happens next: City staff will contact the grant administrator to request a one-year extension and report back to the council. If the extension is not available, councilors may revisit whether to award the current bid, amend the scope, or rebid the work.
Who said what (selected quotes): Allan, presenting options, said the concrete-scope deduction "would be roughly a $20,000 decrease" and cited a reduced base-bid figure of about $76,555. Councilor Lilis urged holding the project until next year if an extension can be secured: "I would make a motion that we hold off until next year and then we budget for it," he said.