Foley approves $229,200 pay estimate as wastewater regionalization nears testing

Foley City Council · July 9, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Foley City Council approved pay estimate No. 19 for the wastewater regionalization project in the amount of $229,200; staff said the Lang lift station testing is targeted for the 23rd and full system startup is anticipated in August.

City Engineer Jared Griffith recommended approval of pay estimate number 19 for the Wastewater Regionalization Project. "The pay estimate is the amount of $229,200," Jared Griffith said, and staff reported the Lang lift station work is progressing with a targeted start-up date around the 23rd for testing and commissioning.

Council members asked whether start-up meant testing or full service; staff clarified the immediate phase is testing pumps, generators and controls to ensure systems operate as designed. Contractors have a punch list of minor restoration items from recent rain events that will be completed prior to final acceptance.

The council moved to approve pay estimate No. 19; the motion carried. Staff said chemical deliveries are scheduled and they are anticipating start-up of the entire system in August, with an inventory and final punch-list work to follow.