Canby council hears resident complaint about 210 Walnut after street project; city to send homeowner letter

Canby City Council · August 8, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Canby council reviewed seal coating plans and a resident’s complaint that a hill at 210 Walnut Ave N. became steeper after street work. Staff presented before-and-after photos and the council recommended sending the homeowner a letter permitting private excavation with a warning that disturbing tree roots could jeopardize the tree; the letter would note removal/replacement costs are the homeowner’s responsibility.

City staff told the Canby City Council on Aug. 8 that the final phase of the street project still has punch-list items to complete and that seal coating is tentatively scheduled for Aug. 22 or 23 without crack-filling. Staff reported coordination with crews to finish remaining work this year.

At issue was a complaint from resident and property owner Lynn Harp (210 Walnut Ave N.) who said the slope of a hill on her property had become steeper after the street project. Sheila Krohse presented before-and-after photographs and said the images showed little to no change in slope. After discussing the evidence and possible remedies, the council recommended the city prepare and send a letter to Harp granting permission to undertake private digging on the homeowner’s property but warning that disturbing roots could jeopardize a nearby tree. The minutes record that if the tree is harmed, cost to remove or replace it would fall to the homeowner.

Council and staff discussed scheduling and scope: the tentative seal coating dates were provided, punch-list items remain to be completed, and no crack-filling will occur before the seal coating. The council did not order remediation work to be performed at city expense; rather, it recommended the written permission with a cautionary statement to the homeowner and further coordination to complete outstanding punch-list items.

The council’s action preserves the city’s planned street work schedule while documenting a homeowner remedy and liability for potential tree damage. Next steps in the minutes include sending the recommended letter and continued coordination with crews to complete punch-list items.