Lee Boulevard study recommends flood wall, roundabouts and realignments with $10M–$16M estimate
Summary
Bolton & Menk presented a final draft Lee Boulevard corridor study recommending Alternative 4 — a flood wall, single-lane roundabouts and roadway realignments — with estimated costs of $10 million to $16 million; the council discussed pedestrian safety and lane reductions.
Get email alerts on the Lee Boulevard Corridor Study topic
No spam. Unsubscribe anytime.
Public Works Director Arnold introduced Kelsey Larsen of Bolton & Menk to present the final draft of the Lee Boulevard corridor study, covering the stretch from Lookout Drive to Belgrade Avenue. Larsen said the study evaluated intersection control, access management and flood mitigation strategies and found most intersections currently operate within typical ranges compared with statewide peers.
The study identified flood risk, access spacing and multimodal needs as key issues. Alternatives examined included raising roadway grades, adding a flood wall with a control gate at Judson Bottom Road, extending the flood wall, and realigning Judson Bottom Road. For safety and operations, the team modeled single-lane roundabouts at Lookout/Lee and Belgrade/Lee, a signal alternative with lane reduction, and various realignments.
The planning team recommended Alternative 4, which combines a flood wall and single-lane roundabouts at Lookout/Lee and Belgrade/Lee, along with realignments of Judson Bottom Road and South Avenue, with planning-level cost estimates between $10 million and $16 million. Council discussion focused on pedestrian safety and whether lane reductions would improve walkability.
No formal decision to proceed with construction was made; the study provides a recommended vision and a planning-level cost range for further design and funding work.