Council approves high‑school change orders and grants safe‑harbor purchase for solar incentives
Summary
Council approved a package of late‑stage change orders the project team classified as operational needs (classroom layouts, custodial spaces, allied‑health flex infrastructure) and authorized a safe‑harbor purchase to secure federal solar incentives for high‑school rooftop PV; project leaders said contingencies remain and overall budget health is strong.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
The Town Council on June 22 approved a set of change orders for the new South Kingstown High School that the project team and the change‑order task force characterized as operational "needs, not wants." Items included confidential workspaces for administrative staff, reconfigured guidance and copy/print locations, custodial lockers, flexible science/instructional reels, a removable mock pharmacy for pharmacy tech instruction, and improvements to the performing‑arts and biomedical lab spaces to accommodate a recently‑awarded anatomy simulation table.
"These are the needs, not the wants," project executive Chris Spiegel told the council after two days of staff walkthroughs identified items that would be costly to retrofit later.
The council also approved a purchase award under a safe‑harbor strategy to secure photovoltaic equipment needed to preserve federal incentives; staff said the procurement is intended to guarantee eligibility for tax and grant incentives before a larger procurement and RFP. Project and finance staff told the council the high‑school project remains "in a healthy place" financially: construction contingency funds and owner contingency balances leave multi‑million dollars of capacity before reaching set project limits.
"We have about $3 million in construction contingency and approximately $6 million in owner contingency remaining," the architect said, and the project manager added that, after previously set‑aside amounts, the team still shows roughly $9 million available if the district were to stop construction immediately. On solar, design staff outlined an estimated installed system cost near $1.5 million with roughly $500,000 in incentives, yielding a net cost in the $1.0–1.2 million range and an expected payback in the 8–10 year range depending on incentives and energy rates.
Councilors praised the educational vision driving decisions — particularly allied‑health and vocational program flexibility — and approved the change orders and the solar equipment safe‑harbor purchase by roll call.