Hampton authorizes Aquarion access for Exeter Road tank work as drought prompts water restrictions

Town of Hampton Select Board · June 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Select Board authorized Aquarion to clear and pave roughly 300 feet of the Exeter Road service road for a replacement water tank and filed for timber cutting; Aquarion and Unitil representatives said a pending company sale will not change local service amid severe drought and outdoor watering restrictions.

The Hampton Select Board on June 22 authorized Aquarion to clear and pave about 300 feet of the Exeter Road service road so a replacement tank can be accessed and construction can proceed.

“Aquarion’s request to use the road is appropriate,” a Board discussion concluded before the motion. The motion to authorize the work and to file an intent to cut timber passed 5‑0‑0. Amanda Keyes, representing Aquarion, said construction will begin this summer and the area will be restored when the project is done.

Carl McMorran, Aquarion, told the Board the current drought condition is severe and groundwater levels are below average; outdoor watering restrictions have been in place since April and some areas that receive water from Seabrook (Sun Valley) already face prohibitions on outdoor water use. The Board and staff noted signage and enforcement steps have been taken for compliance.

Board members also heard that Aquarion is in the process of being acquired by Unitil. Alec O’Meara, Unitil’s director of external affairs, said the multi‑state regulatory acquisition process is nearing finalization, that operational continuity is a priority, and that Unitil will manage municipal relationships going forward.

Officials provided a rough schedule: the new water tank is expected to be completed by the end of 2027 and the old tank removed in early 2028. The Board discussed timing of informative signage and road‑entrance modifications to mitigate neighborhood disruption.

No changes to water quality standards were reported; the discussion focused on supply levels, construction access, and coordination with neighboring Seabrook where supply differs.