Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Energy topic

No spam. Unsubscribe anytime.

Greenburgh staff to redeploy purchased solar panels to rooftops after parking‑lot cost increases

Greenburgh Town Board · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff told the board that shallow bedrock increased parking‑lot canopy costs; because the town already owns purchased panels and incentives are tied to deployed kilowatts, staff recommended moving panels to suitable rooftops (library, multi‑purpose buildings) and pursuing a lease arrangement at Anthony Veteran Park; borings cost and timing were discussed.

Town staff recommended redeploying solar panels purchased for a planned Town Hall parking‑lot canopy after test borings revealed shallow bedrock and unforeseen foundation costs.

Gary Duquesne, commissioner of Community Development and Conservation, told the board that incentives available to support the project total roughly $690,000 and could be as much as $800,000 but that the parking‑lot canopies became expensive because of shallow bedrock. He said the town already owns the panels and advocated placing them on available rooftops (the library, local multipurpose buildings or portions of the Anthony Veteran Park structures) to preserve incentives and lower installation costs.

Duquesne said the Anthony Veteran Park project remains viable as a leased installation (the developer would bear subsurface costs) and that the town could update the contract to reflect rooftop deployments, with an estimated revised town cost between $315,000 and $380,000 depending on configuration. The board asked about test borings (Duquesne estimated borings at about $300,000) and the number of panels remaining (Duquesne said there were more than 100 panels left to deploy). Staff said they would pursue revised contracts and aim to post the Anthony Veteran Park contract for a January meeting.