Summary

Council approved replacing the roof at Fire Station 18 with Legacy Roofing using 26‑gauge metal and a 30‑year warranty at an amount not to exceed $44,000 (including contingency); remaining interior remodels were tabled for 30 days to clarify specifications and warranties.

Council approved a targeted roof replacement at Fire Station 18 and separated that work from a larger package of station renovations.

Council Member Johnson moved to proceed with a roof replacement by Legacy Roofing using 26‑gauge metal and a 30‑year manufacturer's warranty at an amount not to exceed $44,000, including contingency; the motion was seconded and carried on voice vote. Staff earlier explained that Legacy’s original bid was for 29‑gauge metal with a 15‑year warranty but that Legacy agreed to upgrade to 26 gauge and a 30‑year warranty for an additional roughly $6,000 in materials cost, keeping the bid below competing contractors’ proposals.

Council explicitly declined to fund other interior remodel elements at this time and voted separately to table remaining renovation work (Stations 15 and 16 and cosmetic improvements) for 30 days so staff can clarify specifications, warranty differences and cost estimates.

Why it matters: Council separated an urgent repair (roof at Station 18) from a broader renovation package to address immediate safety/maintenance needs while seeking clearer, apples‑to‑apples cost comparisons and warranty information for the remainder of the project.

What’s next: Staff will proceed with the Station 18 roof replacement under the approved not‑to‑exceed amount and will return with clarified bids/specs for the remaining remodel items within 30 days.