Fernandina Beach adopts state-funded flood adaptation plan with 17 strategies and 76 action items

Fernandina Beach City Commission · August 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city adopted a Resilient Florida-funded flood adaptation plan that identifies downtown waterfront and special flood-hazard areas as priorities, outlines 17 strategies with 76 action items, and positions the city to apply for implementation grants for shovel-ready projects.

The Fernandina Beach City Commission voted to adopt a flood adaptation plan developed with funding from the State of Florida’s Resilient Florida program, a presentation and adoption that took place Aug. 19.

Patrick Doty, a senior resilience planner with HAF, told the commission the plan builds on a prior vulnerability assessment and identifies two high-priority areas—the historic downtown waterfront and FEMA-designated special flood-hazard zones. Doty said the plan contains 17 strategies and 76 accompanying actionable items that span nature-based approaches, protection (barriers/floodgates), accommodation (elevating structures), avoidance and managed relocation where necessary. He said the plan was informed by local watershed modeling, a public survey (more than 300 responses) and state statutory guidance tied to Resilient Florida grants.

Doty highlighted that nearly 10% of the city is already affected by tidal flooding during current conditions, with as much as one-third of the city vulnerable in a 100-year storm event, and described implementation pathways that include pursuing available Resilient Florida implementation funding for shovel-ready projects.

Commissioners asked technical questions about the FEMA flood‐map editions and NOAA sea‑level rise curves used to inform the plan; Doty and staff said the plan followed the statutorily prescribed curves but would incorporate newer technically sound data if it met acceptance criteria. Commissioners also discussed developing a resiliency staff position and integrating projects into the capital improvement plan and EAR comprehensive-plan update.

The commission adopted the resolution to formally accept the plan; staff said adoption makes the city eligible for Resilient Florida implementation grant cycles and that staff will prioritize early-action, high-impact projects for funding submissions.

The next steps spelled out by staff include coordinating departmental roles, identifying early-adopter projects, pursuing matching grant funds and returning to the commission with project-specific funding requests as projects become shovel-ready.