City outlines 16‑week Harbor Master Plan phase to coordinate seawall and property owners on North Front Street
Summary
City staff presented a phase‑one scope of work for a Harbor Master Plan (Moffett & Nickel) that would coordinate eight to nine waterfront property owners, integrate a partially designed seawall, and package permitting work with a 16‑week consultant timeline.
Get email alerts on the Harbor Master Plan topic
No spam. Unsubscribe anytime.
City staff presented a two‑phase Harbor Master Plan proposal from Moffett & Nickel focused on redeveloping the north Front Street waterfront and coordinating seawall and resiliency work across multiple property owners.
Staff described phase 1 as an engagement and analysis effort to bring eight or nine property owners together (starting with the Simmons parcel, Beacon Fisheries, Cook & Cook, Goodsell, Cavanagh and the city's parcels) to assess existing permits, permitability and to provide a first‑phase plan for coordinated permitting and permitting packaging to the Army Corps and other regulators. The consultant's work plan estimates a roughly 16‑week timeline and includes baseline condition analyses and property‑owner meetings.
Staff said the city would lead permitting and look to structure easements or maintenance agreements where necessary; if some property owners do not participate, staff said it will develop alternative scenarios to define how far the project can extend. The project would also consider economic development opportunities for participating properties.
Board members asked whether the consultants would present to this board; staff said yes and outlined plans for kickoff meetings and follow‑up consultations. Staff also updated the board on related items: the Waterfront Park grand opening scheduled April 11 and a separate marina redevelopment project advancing through HDC and TRC toward a bid schedule in early April with construction expected after the Shrimp Festival.
The board did not take a vote on the Harbor Master Plan at this meeting; staff said the consultants will return to brief the board as the planning work proceeds.